PETANNA CW10. w/c 31st December 2022

drainage survey / site visit ☑️

treatment plant sized, delivered direct to site ☑️

desludge existing septic tank, supply skip ☑️

sewage treatment plant installed in accordance with manufactures installation / operating manual & building regulations ☑️

septic tank infilled In accordance with current building regulations ☑️

all excavations infilled, excess spoil into skip ☑️

electric connection & certification, part - 2 completed ☑️

building regulations sign off documentation delivered ☑️

skip removed, site left clear, clean and tidy, client happy ☑️

WORK SCHEDULE START TO FINISH ON SITE = 4 working days ☑️